Yorktown Boulevard Bond Project
Everhart Road Traffic Switch
CORPUS CHRISTI, TX – The City of Corpus Christi Traffic Engineering office advises residents and businesses beginning Monday, April 8 at 9:00 a.m. the following traffic control plan will be implemented daily, weather permitting:
-
Northbound and southbound Everhart Road through the Yorktown Boulevard intersection, traffic will shift to the newly constructed pavement on the west side of Everhart Road and remain one lane in each direction.
The city reminds drivers to use caution when driving near the work zone and follow detour signs. Motorists should expect delays and if possible seek alternate routes or avoid the area. Access to local driveways and side streets will be maintained throughout the duration of the project.
For more information, please contact Traffic Engineering at 361-826-3547.