Weekly Road Closures June 8 – June 14
NOTE: ALL CLOSURES ARE SUBJECT TO CHANGE DUE TO WEATHER, EMERGENCY WORK, OR OTHER CURRENT EVENTS.
New – Water Street (Mastec)
Beginning Monday, June 10, 2019, thru Friday, June 14, 2019, contractors are performing utility work on northbound Water Street approaching the Park Avenue intersection. Water Street will be reduced to one northbound lane of traffic through the work area.
New – Eastbound Ayers Street (AEP)
Beginning Monday, June 10, 2019, thru Friday, June 14, 2019, Contractors are performing utility work on eastbound Leopard Street between Battlin Buc Boulevard and Palm Drive. Eastbound Leopard Street will be reduced to one lane of traffic. In addition, northbound Palm Drive will be narrowed approaching the Leopard Street intersection
New – Eastbound Ayers Street (AEP)
Beginning Monday, June 10, 2019, thru Friday, June 14, 2019, Contractors are performing utility work on eastbound Leopard Street between Battlin Buc Boulevard and Palm Drive. Eastbound Leopard Street will be reduced to one lane of traffic. In addition, northbound Palm Drive will be narrowed approaching the Leopard Street intersection
New – Eastbound Ayers Street (AEP)
Beginning Monday, June 10, 2019, thru Friday, June 14, 2019, Contractors are performing utility work on eastbound Ayers Street between Seventh Street and Santa Fe Street. Ayers Street will be reduced to one lane of traffic in each direction.
New - Westbound Ayers Street (AEP)
Beginning Monday, June 10, 2019, thru Friday, June 14, 2019, Contractors are performing utility work on eastbound Ayers Street between Seventh Street and Santa Fe Street. Ayers Street will be reduced to one lane of traffic in each direction.
New – Northbound Carancahua Street (Verveba Telecom)
On Monday, June 10, 2019, Contractors are performing work on the Trinity Towers at 101 Upper Broadway. A large crane will be set up on the Carancahua Street between Coopers Alley and the overhead crosswalk.
Update - Water Street (Mastec North America)
Contractors will be performing utility work on Water Street between Broadway Court and Park Avenue. Work is scheduled thru Friday, June 14, 2019. Both northbound and southbound Water Street will be reduced to one lane of traffic thru the work zone.
New – 5000 Carroll Lane (Vinculums Services)
Beginning Monday, June 10, 2019, thru Tuesday, June 11, 2019, Contractors will be performing utility work on Carroll Lane near the Padre Island Drive (S.P.I.D.) intersection. Northbound Carroll Lane traffic will be closed from S.P.I.D intersection to appoint 400’ approximately north.
New - Staples Street (Video Plumbing)
Contractors are videoing from inside various manholes along Staples Street, from tenth street Brownlee Boulevard. Staples Street will be reduced to one lane of traffic in each direction.
Update - Wooldridge Road (AEP)
Beginning Monday, June 10, 2019, thru Saturday, June 22, 2019, Contractors are performing utility work on Wooldridge Road near the Ennis Joslin Road intersection. Wooldridge Road will be reduced to one lane of traffic and flaggers will be on site to assist motorists through the work zone limits.
Update – North Port (AEP)
On Monday, June 10, 2019, the following temporary traffic control plan will be implemented: during construction hours, Northbound Port Avenue will be reduced to one lane, between Horne Road and Corban Drive.
Update - Laguna Shores Road (E00154, IDIQ)
Contractors are working on utility improvements along Laguna Shores Road between Graham Road and Knickerbocker Street. As this project continues, Laguna Shores is closed to thru traffic between Graham Road and Knickerbocker Street. Motorists should follow the detours around the work area.
The intersection of Park Avenue and Water Street (Mastec North America)
Contractors are working at the intersection of Park Avenue and Water Street. As this project is ongoing, contractors will have the northbound shoulder closed to traffic through the work zone.
Cimarron Boulevard (Tri-Star Contractors)
Contractors are performing utility work on Cimarron Boulevard between Queen Bess Drive and Yorktown Crossing. Work is scheduled thru Tuesday, June 25, 2019. There will be various lane closures based on the contractor’s operations.
Chaparral Street (JMI Constructors)
Contractors are working on the Bayview Tower’s roof located at 400 Mann Street thru Thursday, June 27, 2019. Two parking spaces on the east side (Chaparral Street) of the building will be closed to motorists.
Rodd Field - Saratoga Boulevard to Yorktown Boulevard (E15112, Bond 2014)
Contractors have installed “NEW” STOP Signs and rumble strips on Rodd Field Road at the intersection of the Airline Road Extension. This intersection now operates as an “ALL-WAY” STOP intersection during construction.
Additionally, Police officers are present at the intersections of Slough Road and the Airline Road Extension to assist motorists and traffic flow. Officers will be present, Monday thru Friday, between the hours of 6 AM – 9 AM and 4 PM – 7 PM.
Yorktown Boulevard remains closed to thru traffic between Geiger Drive and Bay Drive.
McArthur Street (IDIQ)
During construction hours, northbound and southbound MacArthur Street, between Roslyn Street and Nimitz Street, will be reduced to one lane for both directions. Flaggers will control traffic around the work zone during construction.
Greenwood Drive and Hemlock Place Intersection (IDIQ)
During construction hours, Hemlock Place intersection at Greenwood Drive will be closed to all traffic. Northbound Greenwood Drive, at Hemlock Place, will be reduced to one lane. Motorists are asked to follow the detour signs around the work zone.
Seagull Boulevard (Harbor Bridge Project)
During construction hours, Contractors will be performing utility work on Seagull Boulevard. The following traffic control plan will be implemented:
- Seagull Boulevard will be closed between Surfboard Avenue and Gulfspray Avenue.
- Surfboard Avenue and Gulfspray Avenue will be closed to traffic from E. Causeway Boulevard to Seagull Boulevard.
- Surfboard Avenue and Gulfspray Avenue will be closed to thru traffic from Timon Boulevard to Seagull.
Airline Road – South Padre Island (SPID) to Holly Road (SPMP)
During construction hours, there will be various lane closures along either northbound or southbound Airline Road, between South Padre Island Drive and Holly Road. At the intersection of Williams Drive, the outside lanes along eastbound and westbound Williams Drive will be closed to traffic. Motorists will still be permitted to make right turns onto Airline Road.
Yorktown Boulevard – Everhart Road to Staples Street (E130196, Bond 2014)
At the intersection of Everhart Road, motorists are advised to follow construction zone signage to guide them through the lane shifts and configuration at the intersection.
Bevly Drive – Lansdown Street to Holmes Drive (SPMP)
Bevly Drive, between Lansdown Street and Holmes Drive, will remain closed to through traffic. Only local residential access will be allowed during the street closure.
Gollihar Road – Weber Road to Staples Street (Project E13087, Bond 2014)
Contractors are performing utility work at the intersection of Gollihar Road and Weber Road. Thru traffic, traveling westbound along Gollihar Road from Staples Street will be prohibited at the Weber Road intersection. Motorists are encouraged to utilize the detour at Carmel Parkway. Local access to businesses and side streets will be provided between Weber Road and Carmel Parkway. Along Weber Road, the following traffic control is implemented:
- Through traffic traveling northbound and southbound along Weber Road will be reduced to one lane in each direction at the Gollihar Road intersection.
- Traffic will shift to the west side of Weber Road through the intersection. East side of Weber Road intersection will be closed.
- Low profile barriers are installed within the Gollihar Road/Weber Road intersection prohibiting left turns and through traffic movements.
- Through traffic heading eastbound along Gollihar Road will be restricted to a “right only” movement on to SB Weber Road.
North Beach Area Road Improvements & Area Beautification (E12127/ E12129, Bond 2012)
North Shoreline Boulevard will be closed from Bridgeport Avenue to Coastal Avenue and will remain in place until this phase of the project is completed. Traffic is reduced to one lane along North Shoreline Boulevard from Pearl Avenue to Bridgeport Avenue. The intersection of Breakwater Avenue is closed at North Shoreline Boulevard. Motorists should follow the detour signs around the work areas.
Old Robstown Road – Highway 44 to Leopard Street (E13098, Bond 2014)
Old Robstown Road is reduced to one lane, in the southbound direction, between Up River Road and Highway 44 (Agnes Street). Motorists at the SH 44 intersection, seeking to go northbound along Old Robstown Road, are encouraged to follow the detour signs around the work zone.
Staples Street - Kostoryz Road to Brawner Parkway (E12095, Bond 2012)
Northbound traffic is shifted onto the southbound lanes along Staples Street, between Texan Trail and Weber Road. Traffic is reduced to one lane of traffic in each direction through the work zone.
South Alameda Street (Ayers Street to Louisiana Avenue E12091, Bond 2012)
Various daily lane closures.
Street Preventive Maintenance Program (SPMP) / Residential Street Rebuild Project (RSRP)
The following Streets are being repaired as part of the City’s Street Preventative Maintenance Program or Residential Street Rebuild Project programs. Motorists are encouraged to be aware of the ongoing construction at these locations:
SPMP
- North Carancahua Street – Lipan Street to Coopers Alley.
- Cimarron Boulevard – Saratoga Boulevard to Yorktown
- Doddridge Street – Ocean Drive to Santa Fe Street
- First National Drive – South Padre Island Drive to Compton Road
- Flour Bluff Drive – Glenoak Drive to Purdue Road
- Glasgow Drive – Timbergate Drive to Ridge Stone Drive
- Louisiana Street – Santa Fe Street to Ocean Drive
- Robert Drive – Alameda Street to Junior Terrace
- Rodd Field Road – South Padre Island Drive to McArdle Road
RSRP
- Acacia Drive – Mueller Street to Interstate Highway 37
- Alameda Street-Rio Vista Drive – Waverly Drive to Alameda Street
- Bevly Drive – Dead End Street to Lansdown Drive
- Bois D Arc Place – Greenwood Drive to Black Jack Place
- Fleet Avenue – Beechcraft Avenue to Ryan Street
- Harriett Drive – Prescott Street to Vestal Street
- Lake Tahoe Drive – Sun Valley Drive to Snowbird Drive
- Lancaster Drive – Leopard Street to Mueller Street
- Moravian Drive – McArdle Road to South Padre Island Drive
- Leigh Drive – Villa Drive to Breckenridge Drive
- O’Hara Drive – Mc Alpin Drive to West Shea Parkway
- Snowbird Drive - Lake Tahoe Drive to Sun Valley Drive
- Yukon Drive – Jordan Drive to Brazos Drive
- Zaragoza Street – Guatemozin Street to Airport Road
For a map of the Citywide Active Street Improvement Projects, please visit https://drive.google.com/open?id=1zKe8B7SdnH50i-g6XMMn7rEZUos&usp=sharing