Street Closures and Traffic Impacts

CORPUS CHRISTI, TX – Street closures along major City streets impacting motorists and pedestrians are listed below. These closures may be due to construction, special event activity, or maintenance. All closures are subject to change due to weather, emergency work, or other circumstances. 

Work zone safety is a priority. Motorists are advised to slow down, follow posted speed limits, pay attention, watch out for workers, obey signs and flaggers, and allow additional travel time for delays.

CITY STREET RECONSTRUCTION OR MAINTENANCE PROJECTS

Brawner Parkway – Kostoryz Road to Carroll Lane (Bond 2018)

During Phase 2 of Brawner Parkway construction, traffic north and south of the median is reduced to one-way in the westbound direction from Carroll Lane to Kostoryz Road.

Fairview Drive – Up River Road to Kenwood Drive (RSRP)

Fairview Drive is closed for street reconstruction between Up River Road and Kenwood Drive. Residents along Fairview Drive will be provided with local access. Construction is expected to last several months.

Junior Beck Road – Bear Lane to Old Brownsville Road (Bond 2018)

During this Phase 2 of the project, Junior Beck Road will be temporarily converted to one-way traffic in the southbound direction from Bear Lane towards Old Brownsville Road. The Corporate Drive intersection at Junior Beck will be temporarily closed for this phase. Residents will continue to have local access from South Padre Island Drive (SPID) Access Road. Wayfinding and detour signage will be in place to guide motorists to their destinations. The temporary one-way and intersection closure is expected to last several months.

Leopard Street – Palm Drive to Nueces Bay Boulevard (Bond 2018) 

Leopard Street is reduced to one lane, in each direction, along the eastbound lanes (south side) of Leopard Street between Nueces Bay Boulevard and Battlin' Buc Boulevard. The intersection at Leopard Street and Nueces Bay Boulevard is open to traffic. Additional temporary intersection closures will be implemented along the south side of Leopard Street as construction progresses.

Long Meadow Drive – Saratoga Boulevard to St. Andrews Drive (Bond 2018)

Traffic on Long Meadow Drive is restricted to one-way only in the northbound direction from Saratoga Boulevard to St. Andrews Drive. Southbound traffic will be detoured to Wooldridge Road to access Everhart Road or Staples Street. The one-way detour is anticipated to last for the duration of the project, and construction is expected to last six months.

Park Road 22 Bridge and Channel – Whitecap Boulevard to Commodores Drive (SH 361) 

Park Road 22 is closed for construction on the south side (eastbound lanes) between Compass Street and Cruiser Street. Motorists traveling eastbound (south side) along Park Road 22 are shifted to the westbound lanes (north side) between Compass Street and Cruiser Street. Travel lanes in each direction are reduced to one lane between Compass Street and Cruiser Street. 

Staples Street – Baldwin Boulevard to Kostoryz Road (Bond 2018) 

During Phase 1 of construction on Staples Street, between Baldwin Boulevard and Kostoryz Road, drivers and pedestrians should expect the following traffic changes:

The northbound lanes and center-turn lane (east side) of Staples Street, between Baldwin Boulevard and Kostoryz Road, will be closed for construction. Traffic will be shifted to the west side of Staples Street (southbound lanes) and reduced to one lane in each direction.

Traffic along northbound Staples Street will be shifted to the west side (southbound lanes) of the roadway approaching the Kostoryz Road intersection.

The inside left-turn lane will be closed along Kostoryz Road at the Staples Street intersection. 

Sidewalks within the construction zone will be closed on the east side of Staples Street. 

Swantner Drive – Indiana Avenue to Texan Trail (Bond 2018) 

Swantner Drive is closed to thru traffic between Ralston Street and Deforrest Street. Swantner Drive from Vaky Street to Glazebrook Street is also closed to thru traffic. Chamberlain Street and McClendon Street are open to local traffic. McCall Street will remain open from Reid Drive to Swantner Drive to allow access to the Lindale Senior Center. 

Reid Drive, Glazebrook Street, and Swantner Drive from Glazebrook Street to Texan Trail are open.

CITY PERMITTED CLOSURES

Alexander Street – Devon Drive to Brentwood Drive 

The contractor for the City will install new ADA ramps along Alexander Street from Devon Drive to Brentwood Drive for James W. Fannin Elementary School as part of the Safe Routes to School program. Temporary sidewalk closures will be implemented, and pedestrians shall follow pedestrian detour signs. Work at this location is expected to last two months.

Caldwell Street – Mexico Street to Brownlee Boulevard (Guerra Underground)

The subcontractor for Flat Iron Dragados is installing a new wastewater line between Mexico Street and Brownlee Boulevard as part of the New Harbor Bridge Utility Relocation Project. Construction is progressing and is now in its final phase. A temporary street closure of Caldwell Street between Mexico Street and Brownlee Boulevard will be in place for the final phase. A temporary intersection closure of Caldwell Street and Mexico Street will be in place as construction progresses to the west. Detour signs will be in place to direct traffic around the temporary street closure. Residents will always have access during construction. Construction is expected to last several months.

Elizabeth Street – Ocean Drive to Third Street

A contractor performing mechanical maintenance is implementing temporary lane closure along Elizabeth Street. The closure is expected to last one day.

Horne Road – Greenwood Drive to Airport Road

A contractor for private development is implementing temporary lane closure along the westbound travel lanes of Horne Road. Closures are expected to last several weeks.

Manitou Street – Rossiter Street to Dead End

The contractor for the Corpus Christi Water Department will repair the wastewater line on Manitou Street. Manitou Street will be temporarily closed to through traffic between Rossiter Street to the dead end. Local residential traffic will have a dedicated access point to enter the work zone. Construction is expected to last 30 days.

Port Avenue – Horne Road to Baldwin Boulevard (Clark Pipeline)

The contractor is replacing a 16-inch water main along South Port Avenue from Horne Road to Baldwin Boulevard. Construction has progressed into the next phase. However, Southbound Port Avenue will remain reduced to one lane between Baldwin Boulevard and Tarlton Street, utilizing the center turn lane as the travel lane. Northbound Port Avenue travel lanes will not be affected. Other lane closures along the project limits may occur for lateral waterline installations. Construction at this location is estimated to last several months.

Port Avenue – at IH 37 Access Road

The subcontractor for Flat Iron Dragados is installing a new water line at the intersection of IH37 Access Road and Port Avenue as part of the New Harbor Bridge Utility Relocation Project. Construction will affect the northbound travel lanes of Port Avenue along the IH37 Access Road intersection. Temporary lane closures will be implemented in both directions to establish a safe work zone. Businesses and residents will always have access to Port Avenue during construction. Construction is expected to last several months.

Santa Fe Street

The contractor for the Corpus Christi Water Department is repairing a wastewater line that runs across Santa Fe Street. To make repairs, contractors will perform daily lane closures on Santa Fe Street between Primrose Drive and Rossiter Street. Construction is expected to last 30 days.

Weber Road – Bahama Drive to Panama Drive

A contractor for the Corpus Christi Water Department is repairing a wastewater line on Weber Road. The contractor will be setting up a wastewater bypass to make repairs. During construction, both directions of Weber Road will be temporarily reduced to one lane between Kingston Drive to Brushwood Lane. Motorists should expect delays when traveling through the work zone. Construction is expected to last 30 days.

SPECIAL EVENTS

Peppermint Lane Holiday Market

The Downtown Management District is hosting a seasonal event every Sunday through December 18. Temporary street closures will be implemented on Chaparral Street between Lawrence Street and Lomax Street. 

ADDITIONAL RESOURCES