Contractor to Complete Final Two Bent Cap Repairs on Yorktown Mud Bridge

Bent Cap Work Nearing Completion

CORPUS CHRISTI, TX – City contractors began repairs to the Yorktown Mud Bridge on January 23. They are now on their 32nd working day of what is expected to be a 70-working-day project.

The project’s current phase calls for restoring nine bridge bent caps. The contractors will complete repairs on the last two bent caps this week. Following the completion of the work on the bent caps, the contractors will prepare the bridge columns for specialized jackets. That work is scheduled to begin next week.