Contractor to Complete Three Bent Cap Repairs on Yorktown Mud Bridge

Project Remains on Schedule

CORPUS CHRISTI, TX – City contractors began repairs to the Yorktown Mud Bridge on January 23. They are now on their 26th working day of what is expected to be a 70-working-day project.

This week the contractors will complete repairs on three bent caps. The project’s current phase calls for restoring 9 of the 11 bridge bent caps. To date, the contractors have completed restorations on four bent caps.

After the work on the bent caps is complete, the contractors will prepare the bridge columns for specialized jackets.