Carroll Lane Bond Project Complete!

CORPUS CHRISTI, TX – The Engineering Services Department and Public Works Department are excited to announce the August 2020 completion of the Bond 2014 Carroll Lane Project from Houston Street to McArdle Road. The $6.5 million project, which began in August 2017, included a brand-new off-street cycle track.

This project also consisted of a full-depth reconstruction of the 2-lane roadway and replacement of the existing asphalt pavement with new asphalt pavement, concrete bus pads, curbs & gutters, sidewalks, ADA ramps, signs, and pavement markings. Utility improvements include water, storm water, gas, and wastewater.

To see a video of the latest improvements on Carroll Lane visit:

Facebook: @citygov

YouTube: CCTVCorpusChristi

CCTV20: Spectrum Channel 1300, Grande Channel 20, AT&T Uverse Channel 99

For more information media representatives can contact Senior Public Information Officer Melanie Lowry at 361-826-3837 or by email at melaniel@cctexas.com

Carroll Lane Project Complete - graphic