Contractors Continue Grout Work on Yorktown Mud Bridge
Contractor Enters 51st Working Day
April 05, 2023
CORPUS CHRISTI, TX – City contractors began repairs to the Yorktown Mud Bridge on January 23. They are now on their 51st working day of what is expected to be a 70-working-day project.
This week, work continues with filling specialized jackets with grout. It will be completed by the end of this week, weather permitting.
Once the grout-filling process is complete, contractors will remove the forms and barges, prepare for surface work, and install guardrails on the bridge.
For more information, media representatives may contact Senior Public Information Officer Richard Vargas at 361-826-3420 or richardv2@cctexas.com.