Cole Park Pier Construction Updates
CORPUS CHRISTI, TX – The City of Corpus Christi Engineering Services Department and the Parks & Recreation Department announce that Phase 1 construction work on the Cole Park Pier Project is underway.
Currently, the contractor is working on demolition of the remaining portion of the pier that is on land and is preparing for the new pier construction. In the coming week, JM Davidson is scheduled to begin the installation of the new Cole Park Pier piles, 59 in total.
The contractor has two barges within the construction site, one barge is being used to support the crane that will perform the installation of the new pier pilings and the other barge is being utilized for equipment and materials transfer.
The Cole Park Pier Project is on schedule and within budget.
For more information, media representatives can contact Engineering Public Information Officer Cynthia Garcia at 361-826-3528 or by email at cynthiag2@cctexas.com.